07-Str-B2
Worked solutions to 8 past sittings (2013–2018), 48 questions. Pick a sitting, or start from a topic below.
Topics across the sittings
Topics that come up in more than one sitting, taken from the headings of our worked solutions. A topic counts once per sitting.
- Engineering Economics (8 sittings): December 2018 Q4 · May 2018 Q4 · December 2017 Q4 · May 2017 Q4 · May 2016 Q4 · May 2014 Q4 · May 2013 Q4 · Undated paper Q4
- Scheduling (8 sittings): December 2018 Q1 · May 2018 Q1 · December 2017 Q1 · May 2017 Q1 · May 2016 Q1 · May 2014 Q2 · May 2013 Q2 · Undated paper Q1
- Regulations (7 sittings): May 2018 Q6 · December 2017 Q6 · May 2017 Q6 · May 2016 Q5 · May 2014 Q6 · May 2013 Q6 · Undated paper Q6
- Safety Practices (7 sittings): May 2018 Q6 · December 2017 Q6 · May 2017 Q6 · May 2016 Q5 · May 2014 Q6 · May 2013 Q6 · Undated paper Q6
- Estimating (5 sittings): December 2018 Q6 · May 2018 Q2 · December 2017 Q3 · May 2016 Q3 · May 2014 Q1
- Contract Administration (4 sittings): December 2018 Q2 · May 2018 Q3 · May 2016 Q2 · Undated paper Q3
- Critical path (4 sittings): December 2018 Q1 · December 2017 Q1 · May 2016 Q1 · May 2013 Q2
- Project Control (4 sittings): December 2018 Q3 · May 2016 Q6 · May 2013 Q1 · Undated paper Q5
- Bid bonds (3 sittings): December 2018 Q5 · December 2017 Q5 · May 2013 Q3
- Delay claims (3 sittings): December 2017 Q2 · May 2017 Q2 · Undated paper Q2
- Insurance (3 sittings): December 2018 Q5 · December 2017 Q5 · May 2013 Q3
- Litigation (3 sittings): December 2017 Q2 · May 2017 Q2 · Undated paper Q2
- Performance bonds (3 sittings): December 2018 Q5 · December 2017 Q5 · May 2013 Q3
- Bidding (2 sittings): May 2016 Q3 · May 2014 Q1
- Cash Flow (2 sittings): May 2018 Q5 · May 2017 Q5
Questions by sitting
December 2018
- Question 1: Scheduling — activity-on-arrow network, floats, critical path and AON conversion
- Question 2: Contract Administration — comparing lump-sum, unit-price, turn-key and cost-plus delivery
- Question 3: Project Control — expense and payment S-curves, financing interest and overdraft limit
- Question 4: Engineering Economics — maximum justifiable investment in a new pavement surface
- Question 5: Insurance — bid bonds, performance bonds and construction liens
- Question 6: Estimating — completing an R.S. Means brick-veneer line and pricing the job
May 2018
- Question 1: Scheduling — CPM with a start-to-start lag, late bar chart and delay impact
- Question 2: Estimating — quantities, durations and bare costs from R.S. Means data
- Question 3: Contract Administration — bid package, competitive bidding, and screening unbalanced bids
- Question 4: Engineering Economics — present-worth comparison of alternatives with unequal lives
- Question 5: Cash Flow — the BCWS curve, and interest on a contractor's overdraft
- Question 6: Safety Practices and Regulations — eight measures on highway and building projects
December 2017
- Question 1: Scheduling — precedence network, floats, critical path, delay impact and percent complete
- Question 2: Litigation — delay claims, contractual prevention, settlement routes and the analyses that support a claim
- Question 3: Estimating — duration and cost from R.S. Means production data, and the activity time–cost relationship
- Question 4: Engineering Economics — present-worth comparison of two projects with unequal lives
- Question 5: Insurance — bid bonds, performance bonds and payment retention, and the advantages of union resources
- Question 6: Safety Practices and Regulations — highway rehabilitation work zones, particularly at night
May 2017
- Question 1: Scheduling — CPM on an activity-on-arrow network and least-cost crashing
- Question 2: Litigation — delay claims, contractual prevention, settlement routes and delay analysis
- Question 3: Productivity — influencing factors, site arrangement, morale and motivation
- Question 4: Engineering Economics — present-worth comparison of two projects with unequal lives
- Question 5: Cash Flow — the S-curve, overdraft interest and the peak cash requirement
- Question 6: Safety Practices and Regulations — night work in highway rehabilitation work zones
May 2016
- Question 1: Scheduling — critical path, total floats, and the effect of delaying E
- Question 2: Contract Administration — bid unbalancing and public-sector award criteria
- Question 3: Estimating and Bidding — indirect-cost classification and the total-indirect-cost equation
- Question 4: Engineering Economics — present-worth comparison of two projects with unequal lives
- Question 5: Safety Practices and Regulations — eight measures across highway and building work
- Question 6: Project Control — S-curves and progress measurement from a bar chart
May 2014
- Question 1: Estimating and Bidding — RS Means unit costs and crew-based duration
- Question 2: Scheduling — precedence network with SS, FS and FF lags
- Question 3: Labor Relations — unionized versus non-unionized labour
- Question 4: Engineering Economics — maximum justified investment in a new pavement surface
- Question 5: Construction Delays — classification and forensic analysis
- Question 6: Safety Practices and Regulations — bridge rehabilitation in high traffic
May 2013
- Question 1: Project Control — earned value and the 20/80 rule
- Question 2: Scheduling — critical path and late bar chart
- Question 3: Insurance — bid bonds, performance bonds and retainage
- Question 4: Engineering Economics — breakeven revenue for alternatives of unequal life
- Question 5: Construction Delays — classification and forensic analysis
- Question 6: Safety Practices and Regulations — a downtown high-rise site
Undated paper
- Question 1: Scheduling — least-cost plan, and accelerating to eight days inside a four-worker limit
- Question 2: Litigation — delay claims, their contractual prevention, and the delay taxonomy
- Question 3: Contract Administration — Design-Bid-Build versus CM at Risk, and screening unbalanced bids
- Question 4: Engineering Economics — present-worth comparison of two projects with unequal lives
- Question 5: Project Control — earned value and the Cost Performance Index under the 20/80 rule
- Question 6: Safety Practices and Regulations — a multi-activity site with demolition and hazardous-material removal